Basement Remodel - 2004-2005
Started with an empty basement with cement walls and floors

Framed, Wired, Plumbed, Insulated, Dry-walled, Finished, Painted
Cut Concrete floor and put in drains
Custom Cabinets, Custom Bar, Full Bathroom and more lighting then anyone should ever need!

Finishing time, over one year. Working on it 4 to 6 times a month. (Owner was in no hurry So I used it as a filler job.)
This project would take about 2 months with the right money and crew.

In the middle of framing, dry-walling, wiring, plumbing etc.
The Bar and Basement are Done!
Working on the Bar
Bar Done!
Under Construction
And we're off...
Done!
Bar Done!
Custom hand-made lighted back panels
with 3 colors switched separately.
Working on it!
 
Click on images to enlarge!
The bathroom
Cut cement floor to put in drain pipes for toilet, shower & sink drains.
Hand-Made back bar lighting & custom cabinets, Made by ME
 